Licence Number

N7L1-1835

Licence Entity

GNWT - Department of Transportation

Licence Status

Expired

Licence Type

Industrial

Notes

Inuvik - Tuktoyaktuk Highway (ITH) kilometre post 0 at the end of Navy Road (Lat 68D 25M 2.857S N, Lon 133D 46M 31.172S W) and kilometre post 119at the junction of the Tuktoyaktuk to Source 177 Access Road (Lat 69D 16M 21.059S N, Lon 132D 54M 11.131S W) - Construction of the Inuvik - Tuktoyaktuk Highway Project Type A water licence with term December 12, 2013 to December 11, 2023.

Reasons for Decision

Water Licence

Water Licence Expiry Reminder

2013-07-15 EISC Letter of Exemption

2013-07-23 Other EISC Letters of Exemption

2013-06-14 Application for Water Licence

2013-06-14 Application for Water Licence (revised)

2013-06-20 Additional Submission Consultation pkg

2013-06-27 Receipt of Application and Review Process

2013-07-03 Completeness and Notice of Application

2013-07-09 Response to Completeness and Notice of Application

2013-07-15 Information Request #1

2013-08-02 Information Request #2

2013-08-06 Request for Extension (IR #2)

2013-08-06 Response to Request for Extension (IR #2)

2013-08-06 Technical Response to IR #1

2013-08-12 Response to IR #1

2013-08-15 Response to IR #2

2013-08-27 NWTWB Response to IRs #1 and #2

2013-08-30 Response to NWTWB Aug. 27/13 Letter

2013-09-05 Additional Information IR #1 and #2

2013-09-10 NWTWB Response to Additional Info IR#1 and #2

2013-09-13 Erratum Additional Information IR #1 and IR #2

2013-09-19 Letter to Inuvik Hunters and Trappers Committee

2013-09-19 Letter to Tuktoyaktuk Hunters and Trappers Committee

2013-09-20 IGC Request for Intervener Status

2013-09-23 NWTWB Response to IGC Letter

2013-09-23 NWTWB Response to IGC Request for Intervener Status

2013-09-24 IHTC Water Licensing Proceeding for ITH

2013-09-24 NWTWB Response to Inuvik Hunters and Trappers Committee

2013-09-27 DOT Additional Submissions

2013-09-27 Inuvialuit Game Council Submission

2013-09-28 FJMC Request for Intervener Status

2013-09-30 NWTWB Response to FJMC Request for Intervener Status

2013-10-31 Information Request

2013-11-03 Response to Information Request

2013-11-04 Response to Information Request (October 31/13)

2013-11-07 Revised Response to Information Request (October 31/13)

2013-11-20 NWTWB ITH Work Plan (Revised)

2013-0704 Request for Review of Application and Comments

2013-07-30 Review of Application and Comments

2013-10-28 Request for Comments on Draft Licence

2013-11-04 Comments on Draft WL

2013-11-04 AANDC Additional Comments on Draft WL

2013-11-05 NWTWB to Reviewers Regarding Late Submission by AANDC

2013-11-07 Reviewers to NWTWB Regarding Late Submission by AANDC

2013-11-13 Decision on Late Submission by AANDC

2013-2014 Annual Report

2013-2014 Annual Report - Revised

2014-07-16 IWB Response to 2013-2014 AR

2014-09-08 IWB Response to Revised 2013-2014 AR

2014-10-10 DOT Response 2013-2014 AR

2014-2015 Annual Report

2015-08-12 IWB Response to 2014-2015 AR

2015-10-15 DOT Response to 2014-2015 AR

2015-2016 Annual Report

2016-07-26 IWB Response to 2015-2016 AR

2016-08-08 DOT Response to 2015-2016 AR

2016-08-11 IWB Acknowledgment - 2015-2016 AR

2016-2017 Annual Report

2017-08-22 IWB Add Info Request - 2016-2017 AR

17-10-06 2016-2017 AR - Revised

2017-11-10 2016-2017 AR - Acknowledgment

2017-2018 Annual Report - Part 1

2017-2018 Annual Report - Part 2

2018-10-02 Annual Report 2017-2018 - Add Info Request

2018-10-11 AR 2017-2018 - INF Add Info Submission

2019-04-12 AR 2017-2018 Revised - Part 2

2019-04-12 AR 2017-2018 Revised - Part 3

2019-04-12 AR 2017-2018 Revised - Part 1

2019-04-24 AR 2017-2018 Acknowledgment

2019-07-17 AR 2018-2019 Reminder

2020-04-16 AR 2018-2019 - Part 1

2020-04-16 AR 2018-2019 - Part 2

2020-04-16 AR 2018-2019 - Part 3

2020-05-14 AR 2018-2019 and SNP - Acknowledgment

2020-06-30 AR 2019-2020

2020-07-07 AR 2019-2020 Add Info Request

2021-04-26 AR 2019-2020 Revised

2021-05-05 AR 2019-2020 Acknowledgment

2021-06-29 AR 2020-2021

2021-07-08 AR 2020-2021 Add Info Request

2021-08-31 AR 2020-2021 INF Response to IWB Add Info Request

2021-09-10 AR 2020-2021 Acknowledgment

2022-06-29 AR 2021-2022

2022-07-27 AR 2021-2022 Add Info Request

2022-2023 Annual Report

2022-2023 Annual Report - Acknowledgment

2014-10-31 1835 SNP Results

2014-11-10 1835 SNP Results

2015-07-10 ITH SNP Lab Results

2016-03-10 Notice to Water Crossing Coordinates Changes

2016-07-19 ITH SNP Lab Results

2016-08-26 ITH SNP Lab Results

2016-10-27 DOT response on SNP sampling 312 and GSC4

2016-11-02 ITH SNP Lab Results

2017-04-28 N7L1-1835 DOT Response on April18, 2017 IR

2017-07-07 ITH SNP Lab Results

2017-08-11 ITH SNP Lab Results

2017-09-08 ITH SNP AEMP sampling delay_Sept 8 2017

2017-09-12 ITH SNP Lab Results

2017-11-06 ITH SNP Lab Results

2017-11-22 ITH Inspection Report

2018-02-20 N7L1-1835 ITH SNP - 2017 Monitoring -Add Info Request

2018-02-27 N7L1-1835 ITH SNP 2017 Monitoring -INF Response on IWB letter Feb 20, 2018

2018-07-11 N7L1-1835 ITH SNP Lab Results

2018-07-13 N7L1-1835 ITH SNP Sampling Delay

2018-08-15 N7L1-1835 DOT-ITH SNP Lab Results

2018-09-21 N7L1-1835 DOT-ITH SNP Lab Results

2018-09-21 N7L1-1835 DOT-ITH SNP Sampling Dealy Notification

2018-11-02 N7L1-1835 ITH SNP Results

2018-11-06 N7L1-1835 ITH Inspection Report

2018-11-26 ITHCWG SNP and Aquatic Effects Monitoring Program

2019-05-31 N7L1-1835 ITH - Inspection Report

2019-08-02 N7L1-1835 INF-ITH SNP Lab Results

2019-10-11 N7L1-1835 ITH 2019 SNP Results - Add Info Req

2020-04-16 N7L1-1835 GNWT -ITH 2019 SNP Report

2020-11-06 N7L1 1835 INF ITH Insp Rep

1835 IR February 14, 2014

1835 IR March 6, 2014

1835 IR April 14, 2014

1835 IR May 20, 2014

1835 IR June 13, 2014

1835 IR November 10, 2014

1835 IR December 01, 2014

1835 IR December 03, 2014

1835 IR December 16, 2014

1835 IR January 6, 2015

1835 IR January 7, 2015

1835 IR January 15, 2015

1835 IR February 3, 2015

1835 IR February 6, 2015

1835 IR February 17, 2015

1835 IR March 5, 2015

1835 IR March 12, 2015

1835 IR March 20, 2015

1835 IR March 31, 2015

2016-01-20 Inspection Report

2016-01-22 Inspection Report

2016-02-04 Inspection Report

2016-02-12 Inspection Report

2016-02-25 Inspection Report

2016-03-04 Inspection Report-N

2016-03-08 Inspection Report South End

2016-04-11 Inspection Report-S

2016-04-12 Inspection Report-N

2016-05-05 Inspection Report-N&S

2016-05-13 WRO Sample Results- May 5, 2016 Inspection

2016-05-05 Inspection Report-N&S

2016-06-02 DOT Response on Inspection Reports

2016-06-06 DOT Response on Inspection Report

2016-06-14 Inspection Report-N&S

160831 Inspection Report- Borrow Source 174

2016-10-18 DOT Response -Source 174 Sinkhole Inspection

2016-11-25 Inspection Report-N&S

2017-02-15 Inspection Report (ITH N&S)

2017-03-02 Inspection Report-N&S(ITH)

2017-03-16 Inspection Report (ITH)

2017-03-29 Inspection Report (ITH)

2017-04-18 ITH Inspection Report

2017-05-05 Inspection Report (ITH)

2017-05-17 Inspection Report (ITH)

2017-06-01 WRO follow-up on IR

2024-05-23 Inspection Report

1835 PD 2013 Cover letter - 130614

1835 PD 2013 Main Report - 130614

1835 PD 2013 Appendix A - 130614

1835 PD 2013 Appendix B - 130614

1835 PD 2013 Appendix C - 130614

1835 PD 2013 Appendix D - 130614

1835 PD 2013 Appendix E - 130614

1835 PD 2013 Appendix E - 130614

1835 PD 2013 Appendix G - 130614

1835 PD 2013 Appendix H - 130614

1835 PD 2013 Appendix I - 130614

1835 Notice of Pre-Hearing Conference - 130812

1835 Notice of Public Hearing - 130823

1835 Pre-Hearing Conference Agenda - 130916

1835 Pre-Hearing Conference Questions - 130916

1835 AANDC PHC Follow-up - 130918

1835 Pre-Hearing Conference Minutes - 130918

1835 Invite to THTC to Attend PH - 130919

1835 Invitation to IHTC to Attend PH - 130919

1835 Supplemental Responses to PHC Questions - 130920

1835 IGC App to Intervene - 130920

1835 Response to IGC App to Intervene - 130923

1835 NWTWB AANDC Participation in Public Hearings - 130924

1835 ILA Participation in Public Hearings - 130924

1835 AANDC Participation in Public Hearings - 130927

1835 DOT Public Hearing Presentation - 130927

1835 FJMC App to Intervene - 130928

1835 Response to FJMC App to Intervene - 130930

1835 Public Hearing Agenda - 131001

1835 IGC Public Hearing Presentation - 131003

1835 FJMC Public Hearing Presentation - 131007

1835 Inuvik Public Hearing Transcripts - 131007

1835 Tuktoyaktuk Public Hearing Transcripts - 131008

1835 test - 131017

1835 Submission as per terms of licence - 131220

1835 As per Terms and Condition of WL- 140110

1835 Response to IWB Mar. 2614 Letter -140428

1835 IWB response - April 28 14 submissions - 140515

1835 Response to IWB May 15, 2014 Letter - 140602

1835 AEMP Revised - 140613

1835 Recent Results of SNP - 140627

1835 IWB Response to AEMP-SNP June 13 submission - 140711

1835 GNWT Response to IWB AEMP-SNP- 140716

1835 IWB response - June 2014 SNP July 16, 2014

1835 IWB response - July AEMP - SNP - 140717

1835 DOT Response IWB Jul.17 IR AEMP-SNP - 140723

1835 IWB Approval of AEMP-SNP - 140725

1835 Source 170 Revised EMP - 140805

1835 Source 177 Revised EMP - 140805

1835 Source I401A Revised EMP - 140805

1835 Preliminary Closure Reclamation Plan - 140815

1835 Updated SNP Result June 2014 - 140815

1835 Source PW 10-11 EMP Mar 1st 2014 - 140902

1835 IWB Response June SNP Additional Info - 140908

1835 IWB response PCRP - 140908

1835 Approval of EMP Revised -140915

1835 Source 170 Perimeter Breach - 140916

1835 Notice Source 170 Perimeter Breach - 140922

1835 IWB response source 170 perimeter breach - 140923

1835 IWB to ENR source 170 Perimeter Breach - 140923

1835 Mapping for Water Sampling Locations - 140924

1835 DOT Response to Sept. 8 and Construction Schedule - 140930

1835 Notice of Late Sampling for September - 141014

1835 DOT SNP Response to IWB - 141015

1835 IWB Response to SNP - 141020

1835 SNP Results - 141031

1835 SNP Results - 141110

1835 Adaptive Management Framework - 141117

1835 IWB Response to Adaptive Mgmt Framework - 141118

1835 Pit Development Plans Source 173-174-305 - 141127

1835 Adapative Mgmt Framework - 141212

1835 Fisheries Management Plan - 141212

1835 IWB Response to Source 173-305-174 PDP - 141212

1835 IWb Response to AMF - 141217

1835 Response to IWB December 12, 2014 Request - 150319

1835 Notice of Plan Changes for Water Crossings - 150326

1835 Approval of Source 174 Pit Development Plan - 150402

1835 Acceptance of Plan Changes for Water Crossings - 150407

1835 SNP-AEMP Annual Sampling - 150515

2015-10-08-FJMC Letter to EIRB

1835 Winter Construction Schedule - 151119

2016-01-22 DOT letter to IWB with update on modifications

2016-01-22 DOT Construction Atlas - Revised

2016-01-27 IWB Response to DOT 2016-01-22 letter

2016-01-29 PDP Submission letter Sources 312 West and GSC 4

2016-02-03 PDP Source 312West Final

2016-02-03 PDP 312 West Appendix A Construction Plan

2016-02-03 PDP 312 West Appendix B-2 Granular Materials Inventory

2016-02-03 PDP 312 West App C Archaeological Site Management Plan

2016-02-03 PDP 312 West Appendix B-1 Geotech Investigation

2016-02-03 PDP Source GSC4 Final

2016-02-03 PDP Source GSC 4 App A Construction Plan

2016-02-03 PDP Source GSC 4 App B Geotech Report

2016-02-08 PDP Source 312 West add info req

2016-02-08 PDP Source GSC 4 add info req

2016-02-24 DOT Respnse to IWB 2016-02-08 add info req - GSC 4

2016-02-24 DOT Response to IWB 2016-02-08 add info req - 312 West

2016-02-24 DOT Response to IWB 2016-01-27 letter

2016-02-29 IWB Response to DOT 2016-02-24 letter

2016-03-01 IWB Response to DOT 2016-02-24 letter - 312 West

2016-03-01 IWB Response to DOT 2016-02-24 letter - GSC 4

2016-03-04 Notice of Operational Change of Source GSC 4

2016-03-07 Notice of Operational Change of Source 312

2016-03-10 Notice to Water Crossing Coordinates Changes

2016-04-04 DOT Letter - Modifications

2016-04-04 DOT letter - 312 West

2016-04-04 DOT Letter - GSC4

2016-05-05 DOT Letter & IFC Embankment Part-1

2016-05-05 IFC Embankment Part-2

2016-05-05 IFC Embankment Part-3

2016-05-05 IFC Embankment Part-4

2016-05-05 IFC Embankment & Adjusted Culverts Part-5

2016-05-10 ITH Commitment Table - Working Copy

2016-05-12 Correspondence and Plan-ESC

2016-05-15 IWB Acceptance - Modifications

2016-05-26 DOT Response -Modifications

2016-08-15 DOT ITH Updated PDP 312 West

2016-08-15 DOT ITH Updated PDP 312 West

2016-08-15 DOT ITH Updated PDP 312 West-Appendix B2 and C

2016-08-16 IWB Letter-Updated PDP Source 312

2016-10-27 DOT Response-SNP Source 312 and GSC4

2016-10-28 Winter Construction Schedule 2016-2017

2016-11-18 Updated Winter Cons Schedule

2016-11-18-Granular Results Pit 312 and GSC4

2017-03-01 DOT Response - Pit 174 Sinkhole

2017-05-09 Impact Mitigation Measures - Design Change

2017-05-10 IWB Response to May 8, 2017 DOT submission

2013-01-31 ITH Land Type and Desin Brief - Ground Thermal Analysis

2013-09-04 ITH_Design_Report

2013-12-27 ITH Emergency Response Management Plan

2016-02-25 GNWT_DOT letter to IWB_GSC4_2016 02 24

2016-05-15 N7L1-1835_Ltr to DOT re Notice of Modifications

2016-05-27 DOT Response – Modifications Response

2016-05-27 DOT Response – Modifications Response

2017-08-18 N7L1-1835 ITH PW10 sediment measures

2018-02-28 N7L1-1835 INF Res on Long Term Impact Design Change

2018-05-04 IWB Resp - Emb Hght reduction

2018-06-11 ITH Pit PW10 Sediment Spill Report

2018-07-04 N7L1-1835 - INF request for reports submission deadline exten

2018-07-06 N7L1-1835 ITH - Reports submission Extension

2018-09-05 N7L1-1835 ITH - INF Submission Extension Request

2020-12-09 N7L1-1837 ITH Submission - Reminder

2013-12-23 Inuvik Waste and Sewage Acceptance Letter

2013-12-23 Tuk Waste and Sewage Acceptance Letter

2013-12-27 ITH Explosives Management Plan

2014-01-20 Spill Contingency Management Plan

2014-01-20 Fish and Fish Habitat Protection Plan

2014-01-20 ITH Permafrost Monitoring Plan

2014-01-20 ITH Wildlife and Wildlife Habitat Protection Plan

2014-03-31 ITH Sediment and Erosion Control Plan- Final

2014-04-25 Waste Management Plan

2014-05-15 IWB response - April 28 14 submissions

2014-07-24 ITH AEMP-SNP July 24 2014(final version)